Skip to main content

Diamond Valley Sports & Fitness Centre

Diamond Valley Sports & Fitness Centre

Location

Greensborough, VIC

Client

Nillumbik Shire Council

Superintendent

Ontoit

Architect

Henderson + Lodge

Contract Type

Construct Only

$16.5m

Project value

12

Months to build

2021

Completed

PROJECT HIGHLIGHTS

  • Restrictive Site Access
  • Existing Structure Works
  • Staged Project Delivery
  • Extensive Demolition Works
  • Compliance Upgrades to Existing Facility

The redevelopment of the Diamond Valley Sports & Fitness Centre was a crucial project that responded to the current and emerging needs of the community and local sporting associations.

The project consisted of extending the existing facility to almost double in size, with new courts and an administration building. The extension is comprised of four new courts for basketball, netball, volleyball and badminton; a new entrance with reception, kiosk and café areas; an expanded gym; and new toilets and change rooms. In addition, some of the existing facility was refurbished with new internal layouts, new finishes and services to suit. The external scope of works consisted of creating new roadways, car parks, pavements, fencing and soft landscaping.

Despite the many challenges faced during construction, this world-class sporting facility was delivered more than five weeks ahead of schedule. A major investment for the council, the new Diamond Valley SFC will be the home for 5,000 plus members and growing.

“This stadium is a special place where many have begun their basketball journey. It’s a tremendous achievement of all involved to deliver a world class facility that our association can now thrive for many years to come.”

Patrick Di LizioGeneral Manager, Diamond Valley Basketball Association

RELATED PROJECTS

Penleigh & Essendon Grammar School Gym

Sandringham College

Club Jubilee One Aquatic Centre & Gym